Location

Stark County, Ohio

IMPACT

HEC-HMS models were used to investigate three potential breach scenarios and HEC-RAS modeling was used for inundation modeling. The project also included the preparation of an Inundation Mapping Memorandum and an Emergency Action Plan (EAP).

Lord’s Lake Dam EAP, Inundation Study/Mapping, and OMI Update

The technical team developed HEC-HMS models that were used to investigate three potential dam breach scenarios, HEC-RAS modeling for inundation modeling, and other ODNR required documents for a privately owned Class I ODNR dam in the headwaters of a small stream that is Stark County, Ohio. The project also included the preparation of an Inundation Mapping Memorandum and an Emergency Action Plan (EAP).